      Gail Francis
      Keymaster
      @gail@reamp.org

       Hi Evaluation Committee,
      Below is Peter and Chinwe’s proposed revision of the timeline for the 3rd party evaluation. The new schedule would allow for a face to face meeting in Detroit prior to the Foundation Working Group in-person meeting. Does anyone have any objection to this schedule? If so, please let me know by COB today. Thanks!

       

      STEP

      DELIVERABLES

      TIMELINE

      REVISED TIMELINE

      1

      Assemble and review RE-AMP and key steward/leader documents

       

      2/14 – 3/1

      2/22 – 3/11

      2

      Interview key stewards and current funders of RE-AMP (15 interviews, identified with Evaluation Committee)

       

      3

      Attend and observe one or more RE-AMP meetings (e.g., of working group, steering committee, Strategic Action Fund), as scheduling permits

       

      2/14 – 3/3

      March & April, as feasible

      4

      Summarize findings-description of network as it is-and present first draft of survey questions for revision

      Initial report to Evaluation Committee

      3 /4

      3/18

      5

      Meet with Evaluation Committee to discuss findings and survey questions; determine need for network mapping and social network analysis

      Facilitated discussion

      Week of 3/7

      3/23 F2F in Detroit

      6

      Complete survey questions & strategy for conducting online survey

      Final survey questions

      3/11

      3/30

      7

      Conduct online survey

       

      3/14 – 4/1

      4/4 – 4/20

      8

      Analyze survey results (may include network connectivity map & social network analysis)

      Draft evaluation report with survey results and connectivity maps

      4/4 – 4/15

      4/20 – 5/2

      9

      Meet with Evaluation Committee to discuss report

      Facilitated teleconference discussion

      Week of 4/18

      Week of 5/9

      10

      Conduct additional interviews of members (15), including key RE-AMP funders

       

      4/25 – 5/6

      5/16 – 5/27

      11

      Produce final report and recommendations

      Final evaluation report

      5/9 – 5/20

      Week of 5/30

      12

      Meet with Steering Committee to discuss recommendations & communication to membership

      Facilitated discussion

      Week of 5/23

      ??


      ——————————————-
      Gail Francis
      L&P Analyst
      RE-AMP
      (715) 945-2164
      Ojibwa, WI
      ampanalyst@gmail.com
      ——————————————-

    • #3696

      Anonymous
      Inactive
      @


      This looks fine to me, Gail. Glad that the face-to-face meeting can take place in conjunction with the other Detroit activities.

      Best,  –Jessica

      ——————————————-
      Jessica Boehland
      Program Officer
      The Kresge Foundation
      Troy, MI
      ——————————————-





      ——————————————-
      Original Message:
      Sent: 02-25-2011 11:31
      From: Gail Francis
      Subject: New Timeline for evaulation

       Hi Evaluation Committee,
      Below is Peter and Chinwe’s proposed revision of the timeline for the 3rd party evaluation. The new schedule would allow for a face to face meeting in Detroit prior to the Foundation Working Group in-person meeting. Does anyone have any objection to this schedule? If so, please let me know by COB today. Thanks!

       

      STEP

      DELIVERABLES

      TIMELINE

      REVISED TIMELINE

      1

      Assemble and review RE-AMP and key steward/leader documents

       

      2/14 – 3/1

      2/22 – 3/11

      2

      Interview key stewards and current funders of RE-AMP (15 interviews, identified with Evaluation Committee)

       

      3

      Attend and observe one or more RE-AMP meetings (e.g., of working group, steering committee, Strategic Action Fund), as scheduling permits

       

      2/14 – 3/3

      March & April, as feasible

      4

      Summarize findings-description of network as it is-and present first draft of survey questions for revision

      Initial report to Evaluation Committee

      3 /4

      3/18

      5

      Meet with Evaluation Committee to discuss findings and survey questions; determine need for network mapping and social network analysis

      Facilitated discussion

      Week of 3/7

      3/23 F2F in Detroit

      6

      Complete survey questions & strategy for conducting online survey

      Final survey questions

      3/11

      3/30

      7

      Conduct online survey

       

      3/14 – 4/1

      4/4 – 4/20

      8

      Analyze survey results (may include network connectivity map & social network analysis)

      Draft evaluation report with survey results and connectivity maps

      4/4 – 4/15

      4/20 – 5/2

      9

      Meet with Evaluation Committee to discuss report

      Facilitated teleconference discussion

      Week of 4/18

      Week of 5/9

      10

      Conduct additional interviews of members (15), including key RE-AMP funders

       

      4/25 – 5/6

      5/16 – 5/27

      11

      Produce final report and recommendations

      Final evaluation report

      5/9 – 5/20

      Week of 5/30

      12

      Meet with Steering Committee to discuss recommendations & communication to membership

      Facilitated discussion

      Week of 5/23

      ??



      ——————————————-
      Gail Francis
      L&P Analyst
      RE-AMP
      (715) 945-2164
      Ojibwa, WI